 DIESEL QUALITY UPGRADATION PROJECT
 

In line with ‘Auto Fuel Policy’, NRL has been producing HSD conforming to BS-II & Euro-III grade up to 90% capacity utilization of Crude Distillation Unit without additional capital investment. For production of Euro-III HSD at 100% capacity utilization to meet requirements of the ‘Auto Fuel Policy’ from April, 2010, NRL is implementing a Diesel Quality Upgradation Project at a project cost of Rs. 434.94 crores.

Ordering of long lead items for the project has been completed and procurement activities for balance materials are in progress. The first phase of project activity for executing tie-in points was successfully completed during the Refinery Turn Around in October-November 2008. Overall Progress of the project as on 15th July, 2009 was 35.43% against schedule of 36.61%. Cumulative expenditure on the project upto 30.06.09 was Rs. 70.02 crores. The Diesel Quality Upgradation Project is expected to be completed by April 2010.
 
 
 
 
 
 
 
© 2006-08 Numaligarh Refinery Limited  | FAQ | SITE INDEX  | MAILS | CONTACT US | DISCLAIMER
Designed by : Web.Com(I) Pvt. Ltd.
Careers Beyond Business Tender Room Right to Information Act 2005